Chisinau rooftop power signal base station

PHOTO // Modernization works at Chisinau Station reach almost

The modernization of the Chisinau 330 kV Station and the expansion of the Vulcanesti 400 kV Electrical Station are essential stages for connecting the Vulcanesti

Progress is being made in the modernization works of the Chisinau Power

The Minister of Energy, Dorin Junghietu, visited the Chisinau Power Station, where the construction works of the foundations of the 330kV and 400 kV equipment for the power

Minister of Energy Dorin Junghietu Inspects Modernization Works

Minister of Energy Dorin Junghietu inspected the Chișinău Power Station today in the context of ongoing modernization works on Moldova''s critical energy infrastructure. At the

Chisinau–Vulcanesti Power Line to Break Moldova''s Energy

Construction began in April 2024 after the technical design received approval. The 158-kilometer transmission line, supported by approximately 508 poles, is part of the €61

Constantin Borosan calls for urgent works at the Chisinau Power

The State Secretary of the Ministry of Energy, Constantin Borosan, has called for urgent works at the Chisinau Electricity Station, where the Vulcanesti-Chisinau High-Voltage

Moldovan energy minister asks to mobilize

The works for the construction of the foundations of the 330 kV and 400 kV equipment for the power autotransformer are underway at

Works on the Vulcănești-Chișinău power line, 70% complete

Construction of the foundations at the Chisinau Power Station has been completed, and assembly of the metal structures for the electrical equipment is currently

Progress is being made in the modernization works of the

The Minister of Energy, Dorin Junghietu, visited the Chisinau Power Station, where the construction works of the foundations of the 330kV and 400 kV equipment for the power

Moldova''s energy crisis: How Ukraine''s offensive and Binzari

The Ukrainian incursion into Russia''s Kursk region and the capture of a strategic natural gas pumping station in the Sudzha district sent shivers down Chisinau.

Ministry of Energy: Urgent modernization works needed at

The Ministry of Energy emphasizes the urgent need to expedite the modernization works at the Chisinau Power Station, which will facilitate the connection to the Vulcănești-Chisinau High

Constantin Borosan calls for urgent works at the Chisinau Power Station

The State Secretary of the Ministry of Energy, Constantin Borosan, has called for urgent works at the Chisinau Electricity Station, where the Vulcanesti-Chisinau High-Voltage

Chisinau Power Plant Begins Installing First Equipment

Construction work on the Vulcanesti-Chisinau transmission line officially began in April 2024 and is part of the Power System Development Project, financed by the World Bank

Chisinau–Vulcanesti Power Line to Break

Construction began in April 2024 after the technical design received approval. The 158-kilometer transmission line, supported by

Ministry of Energy: Urgent modernization works needed at Chisinau Power

The Ministry of Energy emphasizes the urgent need to expedite the modernization works at the Chisinau Power Station, which will facilitate the connection to the Vulcănești-Chisinau High

Moldovan energy minister asks to mobilize resources for as soon

The works for the construction of the foundations of the 330 kV and 400 kV equipment for the power autotransformer are underway at the Chisinau Power Station.

Download PDF Version

PDF includes complete article with source references for printing and offline reading.

Industry news and updates

Get Technical Specifications

Download detailed specifications for our commercial energy storage cabinets, PCS, BMS and EMS systems.

Contact Our Energy Storage Solutions Team

Headquarters

Energy Park Precinct, Unit 15
Johannesburg 2001, South Africa

Phone

+27 10 446 7800

Monday - Friday: 7:30 AM - 5:30 PM SAST